News

Nothing was left to chance

Le Casino est un bâtiment emblématique de la ville de Namur.
Le Casino est un bâtiment emblématique de la ville de Namur.

Combining the construction and renovation of a casino, hotel and car park was an ambitious challenge, expertly delivered by contractor Duchêne. The company can also pride itself on not only meeting the deadlines, but bringing them forward. To the delight of the owners and customers of the Casino de Namur.

“Place your bets, no more bets.” These words, heard in casinos around the world and now tending to disappear as roulette tables become automated, can once again ring out in the capital of Wallonia. The Casino de Namur has had a complete makeover and become Circus Casino Resort de Namur, Belgium’s first and only casino resort. For just over two years, Marc Perin, a site manager at Duchêne for nearly 7 years, expertly managed the project.

The Casino de Namur site includes a hotel that has been renovated and extended.
Hotel and casino guests can enjoy a meal in a modern, pared-back space.
The hotel lobby is also a thoroughfare where casino-goers and restaurant guests cross paths.
A new space for food and drink has been created.

An open-book approach

“The project was managed on the Bouwteam principle, with open books. The client, architects and contractors all played their part and worked together to ensure the project made financial sense for everyone. We found solutions together. This kind of collaboration was crucial for a complex project with strict deadlines. I was fortunate to be involved throughout the entire project, from January 2021 until February 2023, when the building was handed over,” Marc Perin tells us.

The Casino is an iconic building in Namur, and its fairly central location certainly did not make the project any easier, as Marc Perin confirms. “The Casino has a huge impact on the cityscape, and some aspects of the design had to be considered and reconsidered to ensure all parties were fully satisfied.”

The Casino de Namur site includes a hotel that has been renovated and extended: “There were already 50 rooms, which were completely renovated. The internal partitions were retained, while all the building services were upgraded: heating, ventilation and plumbing. The same goes for the flooring, acoustics, finishes and, therefore, painting. We then built a hotel extension, also with 50 rooms, from scratch on a new plot. To create the new entrance to this 100-room hotel, we demolished part of the old casino, namely the staff cloakroom.”

“The Casino’s management also bought a plot of land adjoining the existing building, where we built the extension. The building’s new main entrance, serving the hotel, casino and new brasserie, was created there,” explains Marc Perin.

The hotel also has several seminar rooms, including an existing room that has been renovated.

Acoustics tailored to guests

Building a hotel may seem straightforward, but being part of a casino changes things: “The most challenging aspect of a hotel is the acoustics. That was even more important on this project. Most hotel guests are gamblers, who may play at night and therefore need to sleep during the day. So we improved the blackout in the rooms and paid particular attention to acoustics, to ensure guests’ sleep would not be disturbed by either urban noise or other occupants, whether in the corridor or in neighbouring rooms. The partitions, which house the building services, were therefore reinforced. We also had to deal with quite a few changes during the project. The client wanted to change the flooring, and then the VIP area was enlarged. Despite this, we met the deadlines by working during some holiday periods, at weekends and even on some nights,” says Marc Perin.

The hotel also has several seminar rooms, including an existing room that has been renovated. This broadens the range of activities on offer, with events, shows and poker nights held there. Three other seminar rooms are equipped with videoconferencing systems. This part of the building also houses the VIP room, which opens onto the terrace and includes a bar.

The hotel complex also includes a state-of-the-art gym.

Light and discretion 

The hotel was completely transformed, and so was the casino. Marc Perin lifts the curtain on the new look of this highly secure venue. “The idea was to create a space where everyone could see one another. We therefore had to knock down partitions to open up the whole space.

As some of these partitions supported the old ceilings, those had to be dismantled too. This meant reworking the ventilation system, which had been designed to serve smaller areas. We also reworked the building services at floor level, as each gaming table is connected to the internet. Finally, the flooring, plasterwork and paintwork throughout were renewed.”

“A casino has its own specific requirements. It is usually a fairly dark place. The windows have to be tinted, as this is a legal requirement: people must not be able to see the players from outside. The infrastructure is also particular to the games on offer. Some areas are reserved for gaming and electronic roulette. Everything is managed online, which means several boxes have to be installed in the floor. Lighting is also carefully designed, dimmer in some places and brighter in others,” says Marc Perin.

The casino’s other distinctive feature is security: “There are a huge number of surveillance cameras, as every table has to be monitored. A casino has more cameras than a prison. This means IT plays a major role in the venue, enabling guests to be monitored at all times. That is another way in which it differs from a conventional events venue,” Marc Perin explains.

Luxurious rooms are available to Casino guests.
The seminar rooms are equipped with state-of-the-art multimedia equipment.
The entire project was completed 5 months ahead of the original schedule.

Project completed 5 months ahead of schedule

The entire project was completed not only on time, but 5 months ahead of the original schedule. “The client can therefore start using all the facilities sooner than expected, which is a financial advantage. We can be proud, because we pulled off something nobody believed was possible. Everyone was pulling in the same direction, and even the additional works did not delay the project. Looking back at what we achieved, it was a complete success,” concludes Marc Perin. Duchêne may have been the trump card, but it took the whole team to win the jackpot.  

The hotel façade has been completely refurbished.

Question about this story? Ask your question

In this story

  1. ClientArdent Group
  2. ArchitectBAHG Architecture
  3. Main contractorDuchêne (Groupe Eiffage)

Keep following this

Get an email when a new story is published. No account needed.

What you follow
  • ThemeHospitality design
  • SubjectNews
Share this article

Advertisement

Follow on L’Hotelier

Follow

Follow a project or company and you’ll receive an email whenever a new story appears. Follow a theme or topic and you’ll receive a weekly roundup. No account or password needed: every email includes a link to what you follow.